Experienced project manager with expertise in leading large-scale projects involving diverse teams from various nationalities. Skilled in strategic planning and cross-departmental operations management to ensure efficient production aligned with quality standards. Proficient in problem identification and proactive solution provision, consistently anticipating challenges and implementing effective resolutions. Proven track record of enhancing team performance through mentorship and training initiatives.
When we started prepare for the 2X350 Mw power plant project. We started by managing the construction works of the aboveground facilities with the delay of the coal removal plans.
I primarily managed aboveground auxiliary plants civil structures, the subcontractors to ensure adherence to the Sub Contract, owner specifications, and regulatory requirements as well as to ensure smooth integration with other project components.
I also coordinated to resolve all design and engineering issues.
I was responsible for the preparation of the relevant sections of the draft contract of Power Plant.
Finally I also maintained project schedule, costs forecasts and provide field project engineering coordination with construction contractors. In addition I work with company management to successfully coordinate and integrate the overall project scope, including cost reporting, budget management, schedule, quality and safety.
Assuming the general civil execution and management responsibilities of 2 x 350 MW power plants, related to engineering, design, construction and reporting to the Plant Project Coordinator are some of my duties and responsibilities.
The Project suspended one year later, depending on ressesion of economical issues.
I worked in this project as a site manager, fully authorized civil subcontractor on the timeliness of the construction activities of all concrete structures from the beginning of the project
* Head, manage and supervise a team of Project Controls Engineers and Planners.
* Follow up and implement the established project controls processes and prepare all reporting and deliverables as required.
* Prepare and manage the schedule of the works.
* Manage the contract scope including any claims and variations.
* Manage the invoicing and measurement processes.
* Assist in the procurement of project materials and subcontractors and their subsequent control. Ideal candidate profile.
* Project Controls experience in CCGT power projects.
* Excellent leadership and organization skills, as the successful candidate will lead a team of engineers.
* Competent in Ms Project & Primavera P6.
* Strong problem solving skills: ability to assess a problem and determine an effective course of action.
* Knowledge of engineering, procurement, contracts, construction, and start up work processes.
I worked in this project as a Technical site manager, fully authorized subcontractor on the timeliness of the construction activities of all concrete structures from the beginning of the project. Also Europe's 5th largest cooling tower construction was completed by our company in this project. (158 m high, 55,90 m internal radius).
• Review the Contract documents for each Construction Package and advise the Engineering/Construction Manager of any deficiency.
• Review and continuously monitor, against approved schedules, the Contractor’s major construction progress and ensure equipment and manpower are adequate or in case of any shortage report to Engineering/Construction Manager.
• Review in detail the recovery schedules as submitted by the Contractors and ensure manpower and site supervision staffs are increased properly.
• Regular visits to project sites to validate whether the progress of work on site is in compliance with approved schedules, major milestones have been met and report deficiencies to Construction Manager.
• Review all daily, weekly and monthly reports as submitted by Contractor and report to Construction Manager any deficiency or non-compliance.
• Review any claim involving time impact as submitted by Contractor and report his assessment to Construction Manager.
• Advise the Construction Manager of any foreseen slippage of progress and corrective actions to be taken.
• Attend weekly progress meeting and monthly Executive meetings and participate in preparing the agenda.
• Assist Engineer/Construction Managers during preparation of Monthly Progress reports and Monthly Executive Presentations.
During my time at this company, I participated in two separate projects.
1. Beverage Sector factory Steel Structures Akhisar – Manisa/ TURKEY
2. Izmir Institute of Technology repowered prefabricated buildings with steel Project Urla – İzmir/ Turkey
Project management
Managing Safely - (The Institution of Occupational Safety and Health)
Managing Safely - (The Institution of Occupational Safety and Health)
BEHAVIOUR BASED SUPERVISORY SAFETY LEADER SHIP