Performing HSE checklist for first energization and participate energization
Verifying LOTO prodecure with PTW system for electrical works
Perform electrical inspection for all temporary site panels at project and mobilization site
Review method of statement,JSA for electrical works
The LOTO Coordinator will be the acting Tagging Authority who ensures that all Construction / Startup activities requiring Energy Isolation Permits are executed safely in accordance with the Energy Isolation Management Procedure
The LOTO Coordinator will ensure that the equipment/system safety protective measures are in place prior to the start of the identified work and are removed after the work is completed
Work with Training department to ensure personnel training program for the isolation of hazardous energy is current and complies with the LOTO program requirements
Order and maintain material inventory (Lock Boxes, Locks, Tags, etc.) necessary for the effective implementation of the LOTO program
Provide guidance and direct project personnel on the implementation of the LOTO program
The LOTO Coordinator will maintain a high level of coordination with the client and existing plant operations personnel
Work hours as required, including overtime, weekends and holidays as necessary to support the project
Prepare status reports and give LOTO training presentations to management, client personnel and others as directed
Perform other duties as directed in support of project activities.
Electrical Maintenance Manager
TİM ENDUSTRI
02.2021 - 04.2023
Rehabilitation of Steel Iron Factory
Maintenance of Unit auxiliary and Dry power transformer,156kV Substation, Maintenance of MV and LV panels
MV-LV cable pulling and termination Works.
O&M Electrical Engineer (On site Technical Support)
SCHLUMBERGER (SLB
02.2023 - 01.2023
Act as a technical lever, responsible of designing the Electrical system required to operate facility projects
Review and understand client specifications during proposal phase
Raise clarifications and deviations not inline with Company standards
Create or review the electrical design basis and project specifications
Provide technical requirement for electrical equipment and preliminary MTO’s for electrical bulk material during proposals
Perform technical bid analysis on quotes received from supply chain
Provide inputs to other disciplines during project execution
Participate in engineering meetings
Responsible to deliver electrical engineering documents as per project schedule and in accordance to project budget
Able to design and specify the grounding, lighting, atmospheric protection and cathodic protection systems
Develop the electrical load balance and hazardous area classification drawings considering other disciplines inputs
Perform or review, comment and approve electrical studies
Develop all electrical detail drawings during project execution
Review, comment and approved all outsourced electrical engineering
Review, comment and approved all electrical equipment vendors’ documentation
Lead and assist junior electrical engineers/designers when developing engineering deliverables.
Construction Electrical and I&C Manager
GAMA POWER SYSTEM
01.2020 - 01.2020
Unit auxiliary and Dry power transformer instalation and electrical works
Grounding and lightning works installations
Installation of MV &LV Switchgear
Power&Control cable pulling and Terminations Work
Scada System, MV/LV and instrument cable pulling and termination works
Grounding Measurement
Instrument calibration works
Instrument installation Works.
Construction Electrical Supervisor
TSGI MI SOCAR TURKEY AEGEAN REFİNERY
03.2016 - 12.2019
Supervising the construction of electrical activities at site
Inspecting and reviewing projects to monitor compliance with building and safety codes and other regulations
Ensuring that all the activities at site are as per the project standards
Monitoring job progress and ensure quality work at targeted schedule
Liaising and coordinating with other departments on project issues
Electrical Installation and Pre-Commissioning Works
Underground earthing works
Step-up/step-down transformer
MV/LV Switchgear
UPS system
Generators
Fiber optic, communication and fire alarm system cable pulling and termination works
Busbar Power Distribution
Installation of Power Transformers
Installation of MV &LV Switchgear
Power&Control cable pulling and Terminations Work
Scada System
IR Test
CT-VT Testing
Transformer Testing (Buchholz,OLTC,Oil BDV) ATS/MTS Test
Interlock-Intertrip test with Vendors
Scada Fiber Optic Testing
Grounding Measurement.
Electrical Superintendent
RENAISSANCE HEAVY INSDUSTRIES
04.2019 - 10.2019
Responsible of all electrical works at site and purchasing all electrical project equipment and materials
Unit auxiliary and Dry power transformer installation and electrical works
Generator circuit breaker installation
Grounding and lightning works installations
Fiber optic cable pulling and testing
Siemens Sgen5-100A-2P Turbogenerator Installation and periodic electrical testing
DCS cabinet installation
Boiler instrument cabinet installation works
Instrument calibration laboratory management (instrument calibration and installation works)
Cooling towers electrical and instrumentation works
FGD facilities electrical works
Electrostatic P
Installation.
Electrical QA/AC Engineer
GAMA POWER SYSTEM
09.2013 - 01.2014
Responsible for QA/QC and all documentations
Performing inspections of all electrical work in progress
Coordinate with quality inspections with all the site sub contractors.
Construction Site Engineer
GAMA POWER SYSTEM
08.2012 - 01.2014
DISI, Mudawarra-Amman Water Conveyance System
Step-up/step-down transformer
MV/LV Switchgear
UPS system
Generators and fuel-oil system
Chlorination system
Communication system
Well pumps
MV/LV cable pulling and termination works
Fiber optic, communication and fire alarm system cable pulling and termination works.
Construction Site Engineer
DESAT Elektrik Mekanik A.Ş.
01.2012 - 05.2012
Ant Yapı, Renova Residental Complex Sochi Rooms, 3600 Rooms 3 and 4 star Hotel, Apart Hotel, Administrative Buildings Sport Complexes and Social Facilities
Electrical Works (Power and Control Cabling Infrastructure, Low voltage system cabling, Power System Cabling, Lighting System Cabling).
Construction Site Engineer
DESAT Elektrik Mekanik A.Ş.
06.2010 - 01.2012
Avrasya Metro Group Joint Venture-Kadiköy-Kartal Rail Public Transportation System
Step-up transformer
MV & LV System
MV &LV Switchgear
Power&Control cable pulling and Termination Work
1500Vdc Rigid Catenary System Installation, cabling and termination works