Mr. Acır is an Electrical and Electronics Engineer and is conversant of industrial plant projects both as a Contractor and a Consultant.
Thus, he had the opportunity to experience different aspects of the project such as technical specifications, contract, design, material selection, factory testing, installation, calibration, testing, commissioning and performance evaluation.
As a consultant, apart from the technical studies, he also took an active role in studies such as evaluation of contractual issues, letter writing and report preparation.
As a contractor, he had the opportunity to develop himself in terms of the responsibilities during the operation phase of industrial plants after their construction, as well as the operation and maintenance requirements, problems that may arise and their solutions.
My current goal is to improve myself by being involved in the construction, operation and maintenance of industrial facilities that are more comprehensive and involve different processes.
The following activities were performed in all projects.
PROJECTS
Bandırma Boron and Acid Factories Operating Directorate Turbo Generator Systems and Energy Infrastructure Modernization Construction Work
Client: Eti Mining Operations General Directorate
The overall objective of the Project is to install a 36 MW intermediate drawing fully condensing turbogenerator group and its turbine building, cooling tower, breaker, transformer, diesel generators and all appurtenances connected to them. Moreover, procurement, assembly/disassembly, commissioning of all equipment related to the modernization and integration of the Turbine / Generator (T/G) Group generating 6.3 kV voltage with an installed power of 5.3 kV with two counter pressure currently installed and its integration with the new system.
Construction of Emet Sulfuric Acid Plant
Client: Eti Mining Operations General Directorate
The overall objective of the Project is to construction of a sulfur-based 350,000 tons/year capacity sulfuric acid production facility and auxiliary and ancillary units to meet the needs of steam, electrical energy, water, etc. required for sulfuric acid production.
İskenderun Carbon Black Production Plant
Client: OYAK Sentetik Karbon Ürünleri Sanayi ve Ticaret A.Ş.
The overall objective of the Project is to meet Turkey's entire annual domestic carbon black need of 220 thousand tons and prevents annual carbon black imports of 300 million dollars.
The process tanks, pipe bridges, cable trays, cables, instruments, process pipes, cogeneration and desox units within the scope of the project will be installed by EKON.
Construction and Installation of Ground Bunker Works within the Scope of İsdemir New No. 1 Blast Furnace Project
Client: İskenderun Demir ve Çelik A.Ş.
The overall objective of the Project is to construct a new ground bunker in the existing 437-438 facility area and a conveyor line in the JH-1 junction tower in the blast furnace area.
Mr. Acır has experience in working with local & international experts and has been assigned as designer, inspector, research & development engineer and reporter for more than 7 years mostly for drinking water treatment and wastewater treatment sectors.
He worked in the preparation of technical specification, feasibility studies and cost estimation. He has experience in inspection of electrical works, design review, selection of materials, tests & commissioning and process follow up during DNP.
In addition to working as an electrical & electronics engineer in facility and infrastructure projects, he worked in energy efficiency and renewable energy issues with the YEVDES project.
The following activities were performed in all projects full time at site.
PROJECTS
Revision And Improvement of Pre-Feasibility Studies for Wastewater Treatment Plant Projects and Green & Smart Infrastructure Projects
Client: Ministry of Industry and Technology
The overall objective of the Project is to increase the efficiency, environmental sustainability and competitiveness of selected Organized Industrial Zones (OIZs) in Turkey.
Technical Assistance and Supervision for Rize Wastewater Project EuropeAid/139932/IH/SER/TR” (EU founded) [Construction of Rize Wastewater Treatment Plant (FIDIC Yellow Book)" and "Construction of Rize Wastewater Collection System (FIDIC Red Book)]
Client: Ministry of Environment and Urbanization
The purpose of the contract is to provide Technical Assistance to Rize Municipality and the Project Implementation Unit (PIU) through administrative, financial and technical capacity building, assisting the Municipality in operating an efficient water and wastewater department (Water Utility Department) and to supervise the construction of WWTP, wastewater collection network and pumping stations.
Technical Assistance and Supervision for Sorgun Wastewater Treatment Plant Project - EuropeAid/139547/IH/SER/TR” (EU founded) (FIDIC Yellow Book)
Client: Ministry of Environment and Urbanization
The purpose of the contract is to provide Technical Assistance to Sorgun Municipality and the Project Implementation Unit (PIU) through administrative, financial and technical capacity building and to supervise the construction of Sorgun WWTP and concrete collector.
Technical Assistance and Supervision for Sivas Kızılırmak Right and Left Banks Wastewater Collector Project- EuropeAid/139839/ IH/SER/TR” (EUfounded) (FIDIC Red Book)
Client: Ministry of Environment and Urbanization
The purpose of the contract is to provide Technical Assistance to Municipality/SİBESKİ and the Project Implementation Unit (PIU) through administrative, financial and technical capacity building, assisting the Municipality in operating an efficient water and wastewater department (Water Utility Department) and to supervise the construction of Wastewater Collection System, and 3 pcs pumping stations.
Technical Assistance and Supervision for Çarşamba Wastewater Project - EuropeAid/139609/IH/SER/TR” (EU founded) (FIDIC Yellow Book)
Client: Ministry of Environment and Urbanization
The purpose of the contract is to provide Technical Assistance to Çarşamba Municipality and SASKI and the Project Implementation Unit (PIU) through administrative, financial and technical capacity building, assisting the Municipality in operating an efficient water and wastewater department (Water Utility Department) and to supervise the construction of Çarsamba WWTP, collector lines and pumping stations.
Technical Assistance and Supervision for Kastamonu Wastewater Treatment Plant Project - EuropeAid/139576/IH/SER/TR” (EU founded) (FIDIC Yellow Book)
Client: Ministry of Environment and Urbanization
The purpose of the contract is to provide Technical Assistance to Kastamonu Municipality and the Project Implementation Unit (PIU) through administrative, financial and technical capacity building, assisting the Municipality in operating an efficient water and wastewater department (Water Utility Department) and to supervise the construction of Kastamonu WWTP.
Technical Assistance for Renewable Energy and Energy Efficiency Support for the Municipalities and Universities - EuropeAid/138822/IH/SER/TR
Client: Ministry of Energy and Natural Resources
The overall objective of the project is to promote energy efficiency and renewable energy in line with the EU's resource efficiency.
In terms of energy efficiency, Turkey's legislative framework is partially aligned with the EU acquis. The contract aims to assistance in review of existing strategies, legislative gap analysis, regulatory and sectoral impact assessments, enabling the argumentation for full alignment with EU acquis and, in parallel, with EU policy framework, ensuring.
For this purpose, this project aims at enhancing the capacity of the municipalities and universities in relation to renewable energy and energy efficiency.
Technical Design and Engineering Services for Sludge Management Facilities -UNDP-TUR-FS- 2018-123 (UNDP founded)
Client: Ministry of Environment and Urbanization
The purpose of the contract is to provide Technical Assistance to Kilis Municipality and preparing of technical specification for Construction of Sludge Management Facilities at Kilis WWTP.
Supervision Services for Construction of Waste Water Treatment Plant in Hassa/Hatay within the scope of Turkey Resilience Project in Response to the Syria Crisis -UNDP-TUR-FS-2018/103 (UNDP founded)
Client: Ministry of Environment and Urbanization
The purpose of the contract is to provide Technical Assistance to Hassa Municipality and the Project Implementation Unit (PIU) through administrative and financial and to supervise the construction of Hassa WWTP.
Supervision Services of Akçaabat (Trabzon) Wastewater Project (PPA founded)
Client: Ministry of Environment and Urbanization
The purpose of the contract is to provide Technical Assistance to Akçaabat Municipality, preparing of technical specification for employer requirements and controlling of the facility design.
Technical Assistance and Supervision for Akçaabat Water Supply System Project- EuropeAid/132572/D/WKS/TR (EU founded). (FIDIC yellow book)
Client: Ministry of Environment and Urbanization
The purpose of the contract is to provide Technical Assistance to Akçaabat Municipality and the Project Implementation Unit (PIU) through administrative, financial and technical capacity building, assisting the Municipality in operating an efficient water and wastewater department (Water Utility Department) and to supervise the construction of Akçaabat WTP and the revised reservoirs, transmission raw line and rehabilitation of the existing water supply and distribution system.
Technical Assistance and Supervision for Bartın Water and Wastewater Project- EuropeAid/133841/D/SER/TR (EU founded). (FIDIC yellow book)
Client: Ministry of Environment and Urbanization
The purpose of the contract is to provide Technical Assistance to Bartın Municipality and the Project Implementation Unit (PIU) through administrative, financial and technical capacity building, assisting the Municipality in operating an efficient water and wastewater department (Water Utility Department) and to supervise the construction of Bartın WWTP and the wastewater collection, preliminary treatment and sea outfall in İnkumu and rehabilitation of the existing water supply and distribution system.
Supervision for Construction of the Common Use Facility (CUF) in Tokat under the operation of “Big partnership of small industrialists” - EuropeAid/131549/D/SER/TR). (FIDIC red book)
Client: Ministry of Science, Industry and Technology
The purpose of this project is to carry out the supervision for construction of Common Use Facility (CUF) in Tokat during pre-construction,mobilization, construction, completion of works, defects notification period and contract completion.
The works contract to be implemented under this Operation with the supervision of the Consultant comprises of 3 blocks (A, B and C), with a total area of 3.250 m2.
Microsoft Office
Gonca Kaynak
Environmental Engineer, M.Sc.
+90 534 085 75 25
Serdar Hakkaçırmaz
Director for Türkiye, Central Asia from Eptisa Mühendislik Ltd. Şti.
+90 530 314 09 06
Burak Akpınar
Civil & Structural Group Chief from Ekon Endüstri İnşaat ve Ticaret A.Ş.
+90 544 288 78 53